US 31 over SAND CREEK
This bridge is no longer in the current National Bridge Inventory database, and has likely been demolished or abandoned.
Map
Coordinates:
+39.06500, -85.8333339°03'54" N, 85°49'60" W
Facts
Source: National Bridge Inventory. Information not verified; use at your own risk.
Name: | US 31 over SAND CREEK |
Structure number: | 009210 |
Location: | 07.21 S SR 7 |
Purpose: | Carries highway over waterway |
Route classification: | Major Collector (Rural) [07] |
Length of largest span: | 174.9 ft. [53.3 m] |
Total length: | 354.0 ft. [107.9 m] |
Roadway width between curbs: | 24.0 ft. [7.3 m] |
Deck width edge-to-edge: | 25.3 ft. [7.7 m] |
Vertical clearance above deck: | 14.4 ft. [4.4 m] |
Owner: | State Highway Agency [01] |
Year built: | 1936 |
Year reconstructed: | 1995 |
Historic significance: | Bridge is possibly eligible for the National Register of Historic Places [3] |
Design load: | M 18 / H 20 [4] |
Number of main spans: | 2 |
Main spans material: | Steel [3] |
Main spans design: | Truss - Thru [10] |
Deck type: | Concrete Cast-in-Place [1] |
Wearing surface: | Latex Concrete or similar additive [3] |
Latest Available Inspection: March 2016
Good/Fair/Poor Condition: | Poor |
Status: | Open, no restriction [A] |
Average daily traffic: | 6,732 [as of 2004] |
Truck traffic: | 10% of total traffic |
Deck condition: | Satisfactory [6 out of 9] |
Superstructure condition: | Poor [4 out of 9] |
Substructure condition: | Fair [5 out of 9] |
Structural appraisal: | Meets minimum tolerable limits to be left in place as is [4] |
Deck geometry appraisal: | Basically intolerable requiring high priority of replacement [2] |
Water adequacy appraisal: | Equal to present minimum criteria [6] |
Roadway alignment appraisal: | Somewhat better than minimum adequacy to tolerate being left in place as is [5] |
Channel protection: | Bank is beginning to slump. River control devices and embankment protection have widespread minor damage. There is minor stream bed movement evident. Debris is restricting the channel slightly. [6] |
Scour condition: | Bridge foundations determined to be stable for the assessed or calculated scour condition. [8] |
Sufficiency rating: | 46.5 |
Recommended work: | Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31] |
Estimated cost of work: | $2,237,000 |
Previous Inspections
Date | Condition | Deck | Superstructure | Substructure | ADT | Suff. Rating |
---|
March 2016 | Poor | Satisfactory | Poor | Fair | 6732 | 46.5 |
March 2015 | Poor | Satisfactory | Poor | Fair | 6732 | 46.5 |
March 2013 | Poor | Satisfactory | Poor | Fair | 6732 | 46.5 |
March 2011 | Poor | Satisfactory | Serious | Fair | 6732 | 28.3 |
March 2009 | Fair | Satisfactory | Fair | Satisfactory | 6732 | 61.0 |
March 2007 | Fair | Good | Fair | Satisfactory | 6732 | 57.8 |
March 2005 | Fair | Good | Fair | Satisfactory | 6732 | 56.7 |
April 2003 | Fair | Good | Fair | Satisfactory | 6600 | 56.8 |
April 2001 | Fair | Good | Fair | Satisfactory | 6600 | 56.8 |
July 1999 | Fair | Good | Fair | Satisfactory | 5120 | 57.5 |
September 1997 | Fair | Good | Fair | Satisfactory | 5120 | 57.5 |
August 1995 | Fair | Satisfactory | Fair | Satisfactory | 4995 | 57.4 |
October 1993 | Fair | Satisfactory | Satisfactory | Satisfactory | 4300 | 68.1 |
October 1992 | Fair | Satisfactory | Fair | Satisfactory | 4300 | 57.7 |
September 1989 | Fair | Fair | Fair | Satisfactory | 4300 | 59.9 |