Share:

TWP 183 over OKABENA CREEK

Map

Coordinates:
+43.70786, -95.39543
43°42'28" N, 95°23'44" W

Facts

Source: National Bridge Inventory. Information not verified; use at your own risk.
Name:TWP 183 over OKABENA CREEK
Structure number:2628
Location:0.3 MI N OF JCT CSAH 18
Purpose:Carries highway over waterway
Route classification:Local (Rural) [09]
Length of largest span:60.0 ft. [18.3 m]
Total length:64.0 ft. [19.5 m]
Roadway width between curbs:18.0 ft. [5.5 m]
Deck width edge-to-edge:2.3 ft. [0.7 m]
Owner:Town or Township Highway Agency [03]
Year built:1917
Historic significance:Bridge is eligible for the National Register of Historic Places [2]
Main span material:Concrete [1]
Main span design:Girder and floorbeam system [03]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Gravel [8]

Latest Available Inspection: October 2017

Good/Fair/Poor Condition:Poor
Status:Posted for load [P]
Average daily traffic:10 [as of 1988]
Deck condition:Poor [4 out of 9]
Superstructure condition:Poor [4 out of 9]
Substructure condition:Poor [4 out of 9]
Structural appraisal:Basically intolerable requiring high priority of corrrective action [3]
Deck geometry appraisal:Meets minimum tolerable limits to be left in place as is [4]
Water adequacy appraisal:Better than present minimum criteria [7]
Roadway alignment appraisal:Better than present minimum criteria [7]
Channel protection:Bank is beginning to slump. River control devices and embankment protection have widespread minor damage. There is minor stream bed movement evident. Debris is restricting the channel slightly. [6]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Sufficiency rating:31.0
Estimated cost of work:$500,000,000

Previous Inspections

DateConditionDeckSuperstructureSubstructureADTSuff. Rating
October 2017PoorPoorPoorPoor1031.0
October 2016PoorPoorPoorPoor1031.0
October 2015PoorPoorPoorPoor1031.0
October 2014PoorPoorPoorPoor1031.0
October 2013PoorPoorPoorPoor1031.0
September 2012PoorPoorPoorPoor1031.0
November 2011PoorPoorPoorPoor1031.0
November 2010PoorPoorPoorPoor1031.0
August 2009PoorPoorPoorPoor1031.0
October 2008PoorPoorPoorPoor1031.0
October 2007PoorPoorPoorPoor1048.1
November 2006PoorPoorPoorPoor1048.1
November 2005PoorPoorPoorPoor1048.1
January 2005PoorPoorPoorPoor1048.1
December 2003PoorPoorPoorPoor1048.1
January 2003PoorSeriousPoorSerious1029.1
February 2002PoorPoorPoorPoor1048.1
November 2000PoorPoorPoorPoor1047.7
December 1999PoorPoorPoorFair1047.7
December 1998PoorPoorPoorFair1047.7
December 1997PoorPoorPoorFair1046.9
December 1996PoorPoorPoorFair1046.9
January 1996PoorPoorPoorFair1046.9
January 1995PoorPoorPoorFair1046.9
December 1993PoorPoorPoorFair1046.9
December 1992PoorPoorPoorFair1046.9
December 1991PoorPoorPoorFair1046.9

Element Data

Source: National Bridge Elements dataset, 2018 edition. This feature is experimental.
ElementUnitsQuantity1-Good2-Fair3-Poor4-Serious
Superstructure
Reinforced Concrete Girder/Beamlinear ft.128001280
Deck
Reinforced Concrete Decksq. ft.1,4721,10403680
Wearing Surfacessq. ft.1,1631,04701160
Superstructure
Reinforced Concrete Floor Beamlinear ft.1400102380
Substructure
Reinforced Concrete Abutmentlinear ft.86043430
Bridge Rail
Reinforced Concrete Bridge Raillinear ft.128001280