U.S. 169 over BIRD CREEK
This bridge is no longer in the current National Bridge Inventory database, and has likely been demolished or abandoned.
Map
Coordinates:
+36.23927, -95.8480136°14'21" N, 95°50'53" W
Facts
Source: National Bridge Inventory. Information not verified; use at your own risk.
Name: | U.S. 169 over BIRD CREEK |
Structure number: | 152010000000000 |
Location: | 7 MI N JCT I-44 |
Purpose: | Carries highway over waterway |
Route classification: | Principal Arterial - Other Freeways or Expressways (Urban) [12] |
Length of largest span: | 180.1 ft. [54.9 m] |
Total length: | 388.1 ft. [118.3 m] |
Roadway width between curbs: | 29.9 ft. [9.1 m] |
Deck width edge-to-edge: | 32.2 ft. [9.8 m] |
Vertical clearance above deck: | 16.1 ft. [4.9 m] |
Owner: | State Highway Agency [01] |
Year built: | 1960 |
Year reconstructed: | 1979 |
Historic significance: | Bridge is not eligible for the National Register of Historic Places [5] |
Design load: | M 18 / H 20 [4] |
Main span material: | Steel [3] |
Main span design: | Truss - Thru [10] |
Deck type: | Concrete Cast-in-Place [1] |
Wearing surface: | Low slump Concrete [4] |
Latest Available Inspection: July 2013
Good/Fair/Poor Condition: | Poor |
Status: | Open, no restriction [A] |
Average daily traffic: | 28,150 [as of 2013] |
Truck traffic: | 8% of total traffic |
Deck condition: | Fair [5 out of 9] |
Superstructure condition: | Poor [4 out of 9] |
Substructure condition: | Poor [4 out of 9] |
Structural appraisal: | Meets minimum tolerable limits to be left in place as is [4] |
Deck geometry appraisal: | Meets minimum tolerable limits to be left in place as is [4] |
Water adequacy appraisal: | Equal to present minimum criteria [6] |
Roadway alignment appraisal: | Equal to present minimum criteria [6] |
Channel protection: | Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7] |
Pier/abutment protection: | Navigation protection not required [1] |
Scour condition: | Countermeasures have been installed to mitigate an existing problem with scour. [7] |
Sufficiency rating: | 43.1 |
Recommended work: | Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31] |
Estimated cost of work: | $4,591,000 |
Previous Inspections
Date | Condition | Deck | Superstructure | Substructure | ADT | Suff. Rating |
---|
July 2013 | Poor | Fair | Poor | Poor | 28150 | 43.1 |
May 2011 | Fair | Satisfactory | Fair | Fair | 27400 | 48.8 |
June 2009 | Fair | Fair | Fair | Satisfactory | 27450 | 47.8 |
August 2007 | Fair | Satisfactory | Satisfactory | Satisfactory | 43650 | 52.8 |
November 2006 | Fair | Satisfactory | Satisfactory | Satisfactory | 42500 | 52.8 |
July 2005 | Fair | Satisfactory | Satisfactory | Satisfactory | 44000 | 63.0 |
January 2004 | Fair | Satisfactory | Satisfactory | Satisfactory | 51550 | 63.0 |
January 2003 | Fair | Satisfactory | Satisfactory | Satisfactory | 25490 | 63.0 |
September 2000 | Good | Good | Good | Good | 25490 | 63.0 |
August 2000 | Good | Good | Good | Good | 25490 | 63.0 |
September 1998 | Fair | Good | Satisfactory | Good | 25490 | 51.8 |
September 1996 | Fair | Good | Satisfactory | Good | 21040 | 51.8 |
December 1994 | Fair | Good | Satisfactory | Satisfactory | 16000 | 58.0 |
August 1992 | Fair | Good | Satisfactory | Satisfactory | 14500 | 58.0 |