Source: National Bridge Inventory. Information not verified; use at your own risk.
Name: | SR 0390 TR 390 over BRIDGE CREEK |
Structure number: | 000000000029880 |
Old structure number: | 510390007000000 (from 1992 edition) |
Location: | GREENE TWP .2 M N SR 3002 |
Purpose: | Carries highway over waterway |
Route classification: | Minor Arterial (Rural) [06] |
Length of largest span: | 42.0 ft. [12.8 m] |
Total length: | 43.0 ft. [13.1 m] |
Roadway width between curbs: | 27.6 ft. [8.4 m] |
Deck width edge-to-edge: | 29.9 ft. [9.1 m] |
Owner: | State Highway Agency [01] |
Year built: | 1953 |
Historic significance: | Bridge is not eligible for the National Register of Historic Places [5] |
Design load: | M 18 / H 20 [4] |
Main span material: | Steel [3] |
Main span design: | Stringer/Multi-beam or girder [02] |
Deck type: | Closed Grating [4] |
Wearing surface: | Bituminous [6] |
Latest Available Inspection: June 2017
Good/Fair/Poor Condition: | Poor |
Status: | Open, no restriction [A] |
Average daily traffic: | 1,506 [as of 2017] |
Truck traffic: | 3% of total traffic |
Deck condition: | Poor [4 out of 9] |
Superstructure condition: | Fair [5 out of 9] |
Substructure condition: | Fair [5 out of 9] |
Structural appraisal: | Somewhat better than minimum adequacy to tolerate being left in place as is [5] |
Deck geometry appraisal: | Meets minimum tolerable limits to be left in place as is [4] |
Water adequacy appraisal: | Equal to present desirable criteria [8] |
Roadway alignment appraisal: | Equal to present minimum criteria [6] |
Channel protection: | Bank and embankment protection is severely undermined. River control devices have severe damage. Large deposits of debris are in the channel. [4] |
Scour condition: | Bridge is scour critical; bridge foundations determined to be unstable. [3] |
Sufficiency rating: | 62.4 |
Recommended work: | Widening of existing bridge with deck rehabilitation or replacement. [34] |
Estimated cost of work: | $302,000 |
Previous Inspections
Date | Condition | Deck | Superstructure | Substructure | ADT | Suff. Rating |
---|
June 2017 | Poor | Poor | Fair | Fair | 1506 | 62.4 |
June 2015 | Poor | Poor | Fair | Fair | 1488 | 62.4 |
June 2013 | Poor | Poor | Fair | Fair | 992 | 72.2 |
June 2011 | Poor | Poor | Fair | Satisfactory | 983 | 73.2 |
June 2009 | Poor | Poor | Fair | Satisfactory | 1729 | 70.6 |
June 2007 | Poor | Poor | Fair | Satisfactory | 1673 | 70.7 |
May 2005 | Poor | Poor | Fair | Satisfactory | 1577 | 71.9 |
September 2004 | Poor | Poor | Fair | Satisfactory | 1164 | 72.8 |
July 2003 | Poor | Poor | Fair | Satisfactory | 1141 | 72.8 |
May 2002 | Poor | Poor | Satisfactory | Good | 1113 | 83.6 |
July 2001 | Poor | Poor | Satisfactory | Good | 1100 | 79.4 |
August 1999 | Poor | Poor | Satisfactory | Good | 1497 | 77.6 |
October 1998 | Poor | Poor | Satisfactory | Good | 1460 | 78.7 |
February 1998 | Poor | Poor | Satisfactory | Good | 1109 | 79.4 |
April 1996 | Poor | Poor | Good | Good | 1428 | 78.8 |
June 1994 | Poor | Poor | Good | Poor | 1357 | 53.2 |
September 1992 | Poor | Poor | Good | Poor | 1320 | 53.3 |
December 1990 | Fair | Fair | Good | Good | 1210 | 84.0 |
Element Data
Source: National Bridge Elements dataset, 2019 edition. This feature is experimental.
Element | Units | Quantity | 1-Good | 2-Fair | 3-Poor | 4-Serious |
---|
Superstructure |
Steel Girder/Beam | linear ft. | 336 | 84 | 252 | 0 | 0 |
Steel Protective Coating | sq. ft. | 10,753 | 10,753 | 0 | 0 | 0 |
Substructure |
Reinforced Concrete Abutment | linear ft. | 121 | 113 | 7 | 1 | 0 |
Deck |
Concrete Filled Grid Deck | sq. ft. | 1,178 | 1 | 1,177 | 0 | 0 |
Wearing Surfaces | sq. ft. | 1,178 | 1 | 1,177 | 0 | 0 |
Bearings |
Fixed Bearing | each | 16 | 16 | 0 | 0 | 0 |
Steel Protective Coating | sq. ft. | 10,753 | 10,753 | 0 | 0 | 0 |
Bridge Rail |
Steel or Aluminum Bridge Rail | linear ft. | 86 | 70 | 12 | 4 | 0 |
Steel Protective Coating | sq. ft. | 10,753 | 10,753 | 0 | 0 | 0 |