Share:

FAP 10 over BIG GOOSE CREEK

Map

Coordinates:
+36.38508, -86.13083
36°23'06" N, 86°07'51" W

Facts

Source: National Bridge Inventory. Information not verified; use at your own risk.
Name:FAP 10 over BIG GOOSE CREEK
Structure number:85SR0100019
Location:IN HARTSVILLE
Purpose:Carries highway over waterway
Route classification:Minor Arterial (Rural) [06]
Length of largest span:53.2 ft. [16.2 m]
Total length:245.1 ft. [74.7 m]
Roadway width between curbs:25.9 ft. [7.9 m]
Deck width edge-to-edge:32.2 ft. [9.8 m]
Owner:State Highway Agency [01]
Year built:1949
Historic significance:Historical significance is not determinable at this time [4]
Design load:M 18 / H 20 [4]
Number of main spans:6
Main spans material:Concrete [1]
Main spans design:Tee beam [04]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Bituminous [6]

Latest Available Inspection: February 2017

Good/Fair/Poor Condition:Fair
Status:Open, no restriction [A]
Average daily traffic:7,580 [as of 2015]
Truck traffic:8% of total traffic
Deck condition:Fair [5 out of 9]
Superstructure condition:Fair [5 out of 9]
Substructure condition:Fair [5 out of 9]
Structural appraisal:Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck geometry appraisal:Basically intolerable requiring high priority of corrrective action [3]
Water adequacy appraisal:Better than present minimum criteria [7]
Roadway alignment appraisal:Equal to present desirable criteria [8]
Channel protection:Bank and embankment protection is severely undermined. River control devices have severe damage. Large deposits of debris are in the channel. [4]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Sufficiency rating:43.9
Recommended work:Widening of existing bridge or other major structure without deck rehabilitation or replacement [33]
Estimated cost of work:$1,082,000

Previous Inspections

DateConditionDeckSuperstructureSubstructureADTSuff. Rating
February 2017FairFairFairFair758043.9
February 2015FairFairFairFair681043.9
February 2013FairSatisfactorySatisfactorySatisfactory656050.8
March 2011FairGoodGoodSatisfactory623052.8
February 2009FairGoodGoodSatisfactory670063.6
March 2007FairGoodGoodSatisfactory689063.6
March 2005FairGoodGoodSatisfactory724063.6
March 2003FairGoodGoodSatisfactory675065.6
May 2001FairGoodGoodSatisfactory645065.6
May 1999FairGoodGoodSatisfactory725065.6
April 1997FairGoodGoodSatisfactory679058.4
June 1995FairGoodGoodFair619047.5
September 1993FairGoodGoodSatisfactory708058.4
October 1991FairGoodGoodSatisfactory666065.9