Facts

Source: National Bridge Inventory. Information not verified; use at your own risk.
Name:W 7TH STREET over FOREST PRK LN-TRINITY RI
Structure number:022200ZZ7600001
Location:W 7TH OVER FOREST PRK BLV
Purpose:Carries highway over highway and waterway
Route classification:Other Principal Arterial (Urban) [14]
Length of largest span:137.1 ft. [41.8 m]
Total length:975.1 ft. [297.2 m]
Roadway width between curbs:47.9 ft. [14.6 m]
Deck width edge-to-edge:58.1 ft. [17.7 m]
Vertical clearance below bridge:17.4 ft. [5.3 m]
Skew angle:13°
Owner:City or Municipal Highway Agency [04]
Year built:1913
Year reconstructed:1955
Historic significance:Bridge is possibly eligible for the National Register of Historic Places [3]
Design load:M 18 / H 20 [4]
Number of main spans:3
Main spans material:Concrete continuous [2]
Main spans design:Tee beam [04]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Bituminous [6]

Latest Available Inspection: March 2012

Good/Fair/Poor Condition:Poor
Status:New structure not yet open to traffic [G]
Average daily traffic:22,770 [as of 2009]
Truck traffic:1% of total traffic
Deck condition:Fair [5 out of 9]
Superstructure condition:Poor [4 out of 9]
Substructure condition:Fair [5 out of 9]
Structural appraisal:Meets minimum tolerable limits to be left in place as is [4]
Deck geometry appraisal:Basically intolerable requiring high priority of replacement [2]
Underclearances appraisal:Meets minimum tolerable limits to be left in place as is [4]
Water adequacy appraisal:Equal to present desirable criteria [8]
Roadway alignment appraisal:Equal to present desirable criteria [8]
Channel protection:Banks are protected or well vegetated. River control devices such as spur dikes and embankment protection are not required or are in a stable condition. [8]
Pier/abutment protection:Navigation protection not required [1]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Sufficiency rating:34.0
Recommended work:Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Estimated cost of work:$6,594,000

Previous Inspections

DateConditionDeckSuperstructureSubstructureADTSuff. Rating
March 2012PoorFairPoorFair2277034.0
December 2010PoorFairPoorFair1201038.8
March 2010PoorFairPoorFair1201038.8
December 2008PoorFairPoorFair1201038.8
December 2007PoorFairPoorFair1201038.8
February 2007PoorFairPoorFair1201038.8
March 2004PoorFairPoorFair1914032.9
March 2002PoorFairPoorFair1914029.3
February 2000PoorFairPoorFair1914029.3
March 1998PoorFairPoorFair1914029.3
November 1996PoorFairPoorFair1914029.3