PattersonFordRd749 over Big Walker Creek
Map
Coordinates:
+37.25805, -80.7129237°15'29" N, 80°42'47" W
Facts
Source: National Bridge Inventory. Information not verified; use at your own risk.
Name: | PattersonFordRd749 over Big Walker Creek |
Structure number: | 000000000008508 |
Location: | 0.10-Rte 811;0.00-deadend |
Purpose: | Carries highway over waterway |
Route classification: | Local (Rural) [09] |
Length of largest span: | 3.9 ft. [1.2 m] |
Total length: | 107.9 ft. [32.9 m] |
Roadway width between curbs: | 11.2 ft. [3.4 m] |
Deck width edge-to-edge: | 12.1 ft. [3.7 m] |
Owner: | State Highway Agency [01] |
Year built: | 1950 |
Historic significance: | Bridge is not eligible for the National Register of Historic Places [5] |
Main span material: | Steel [3] |
Main span design: | Culvert [19] |
Deck type: | Concrete Cast-in-Place [1] |
Latest Available Inspection: August 2018
Good/Fair/Poor Condition: | Poor |
Status: | Posted for load [P] |
Average daily traffic: | 71 [as of 2014] |
Structural appraisal: | Meets minimum tolerable limits to be left in place as is [4] |
Deck geometry appraisal: | Basically intolerable requiring high priority of corrrective action [3] |
Water adequacy appraisal: | Equal to present minimum criteria [6] |
Roadway alignment appraisal: | Basically intolerable requiring high priority of corrrective action [3] |
Channel protection: | Bank protection is being eroded. River control devices and/or embankment have major damage. Trees and rush restrict the channel. [5] |
Culvert condition: | Large spalls, heavy scaling, wide cracks, considerable efflorescence or opened construction joint permitting loss of backfill. Considerable settlement or misalignment. Considerable scouring or erosion at curtain walls, wingwalls or pipes. Metal culverts have significant distortion and deflection throughout, extensive corrosion or deep pitting. [4] |
Scour condition: | Bridge foundations determined to be stable for assessed or calculated scour conditions; field review indicates action is required. [4] |
Sufficiency rating: | 48.4 |
Recommended work: | Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31] |
Estimated cost of work: | $2,585,000 |
Previous Inspections
Date | Condition | Culvert Condition | ADT | Suff. Rating |
---|
August 2018 | Poor | 4 out of 10 | 71 | 48.4 |
August 2017 | Poor | 4 out of 10 | 71 | 48.4 |
August 2016 | Poor | 4 out of 10 | 71 | 48.4 |
August 2015 | Poor | 4 out of 10 | 71 | 48.4 |
August 2014 | Poor | 4 out of 10 | 48 | 48.9 |
August 2013 | Fair | 5 out of 10 | 48 | 57.3 |
August 2011 | Fair | 5 out of 10 | 48 | 57.3 |
August 2010 | Fair | 5 out of 10 | 48 | 57.3 |
August 2009 | Fair | 5 out of 10 | 48 | 60.3 |
August 2008 | Poor | N out of 10 | 14 | 46.7 |
January 2008 | Poor | N out of 10 | 14 | 46.7 |
February 2007 | Poor | N out of 10 | 12 | 46.7 |
February 2006 | Poor | N out of 10 | 12 | 46.7 |
January 2005 | Poor | N out of 10 | 12 | 46.7 |
May 2003 | Poor | N out of 10 | 12 | 47.0 |
May 2002 | Poor | N out of 10 | 20 | 47.0 |
May 2001 | Poor | N out of 10 | 20 | 47.0 |
May 2000 | Poor | N out of 10 | 20 | 47.0 |
April 1999 | Poor | N out of 10 | 20 | 47.0 |
April 1997 | Fair | N out of 10 | 20 | 60.0 |
June 1996 | Fair | N out of 10 | 14 | 60.0 |
June 1995 | Fair | N out of 10 | 14 | 60.0 |
June 1994 | Fair | N out of 10 | 14 | 60.0 |
June 1993 | Fair | N out of 10 | 14 | 60.0 |
June 1992 | Fair | N out of 10 | 14 | 70.4 |
June 1990 | Fair | N out of 10 | 14 | 70.4 |