WV RT 39 over BELLS CREEK
This bridge is no longer in the current National Bridge Inventory database, and has likely been demolished or abandoned.
Map
Coordinates:
+38.23167, -81.1950038°13'54" N, 81°11'42" W
Facts
Source: National Bridge Inventory. Information not verified; use at your own risk.
Name: | WV RT 39 over BELLS CREEK |
Structure number: | 00000000034A056 |
Location: | 0.20 MI W OF CR 16/6 |
Purpose: | Carries highway over waterway |
Route classification: | Major Collector (Rural) [07] |
Length of largest span: | 58.1 ft. [17.7 m] |
Total length: | 123.0 ft. [37.5 m] |
Roadway width between curbs: | 24.3 ft. [7.4 m] |
Deck width edge-to-edge: | 26.6 ft. [8.1 m] |
Skew angle: | 25° |
Owner: | State Highway Agency [01] |
Year built: | 1929 |
Historic significance: | Bridge is possibly eligible for the National Register of Historic Places [3] |
Number of main spans: | 2 |
Main spans material: | Concrete continuous [2] |
Main spans design: | Arch - Deck [11] |
Deck type: | Not applicable [N] |
Wearing surface: | Bituminous [6] |
Latest Available Inspection: February 2010
Good/Fair/Poor Condition: | Poor |
Status: | Posted for load [P] |
Average daily traffic: | 3,400 [as of 2006] |
Truck traffic: | 11% of total traffic |
Superstructure condition: | Serious [3 out of 9] |
Substructure condition: | Poor [4 out of 9] |
Structural appraisal: | Basically intolerable requiring high priority of corrrective action [3] |
Deck geometry appraisal: | Basically intolerable requiring high priority of replacement [2] |
Water adequacy appraisal: | Superior to present desirable criteria [9] |
Roadway alignment appraisal: | Better than present minimum criteria [7] |
Channel protection: | Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7] |
Scour condition: | Bridge foundations determined to be stable for the assessed or calculated scour condition. [8] |
Sufficiency rating: | 13.2 |
Recommended work: | Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31] |
Estimated cost of work: | $1,846,000 |
Previous Inspections
Date | Condition | Deck | Superstructure | Substructure | ADT | Suff. Rating |
---|
February 2010 | Poor | - | Serious | Poor | 3400 | 13.2 |
February 2000 | Poor | - | Serious | Poor | 3000 | 13.2 |
February 1990 | Poor | - | Poor | Fair | 3600 | 21.2 |