CR 292-H- DEAN LN over BORROW CREEK

This bridge is no longer in the current National Bridge Inventory database, and has likely been demolished or abandoned.

Map

Coordinates:
+35.46811, -90.60091
35°28'05" N, 90°36'03" W

Facts

Source: National Bridge Inventory. Information not verified; use at your own risk.
Name:CR 292-H- DEAN LN over BORROW CREEK
Structure number:000000000020436
Location:.03 MI SE JCT CR 297
Purpose:Carries highway over waterway
Route classification:Local (Rural) [09]
Length of largest span:37.1 ft. [11.3 m]
Total length:137.1 ft. [41.8 m]
Roadway width between curbs:17.1 ft. [5.2 m]
Deck width edge-to-edge:17.1 ft. [5.2 m]
Owner:County Highway Agency [02]
Year built:1985
Historic significance:Historical significance is not determinable at this time [4]
Design load:M 18 / H 20 [4]
Number of main spans:4
Main spans material:Steel [3]
Main spans design:Stringer/Multi-beam or girder [02]
Deck type:Open Grating [3]
Wearing surface:Other [9]

Latest Available Inspection: February 2016

Good/Fair/Poor Condition:Good
Status:Open, no restriction [A]
Average daily traffic:39 [as of 1987]
Truck traffic:1% of total traffic
Deck condition:Good [7 out of 9]
Superstructure condition:Good [7 out of 9]
Substructure condition:Good [7 out of 9]
Structural appraisal:Better than present minimum criteria [7]
Deck geometry appraisal:Basically intolerable requiring high priority of corrrective action [3]
Water adequacy appraisal:Better than present minimum criteria [7]
Roadway alignment appraisal:Equal to present minimum criteria [6]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Pier/abutment protection:None present but re-evaluation suggested [5]
Scour condition:Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Sufficiency rating:83.9
Recommended work:Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Estimated cost of work:$371,000

Previous Inspections

DateConditionDeckSuperstructureSubstructureADTSuff. Rating
February 2016GoodGoodGoodGood3983.9
January 2014GoodGoodGoodGood3983.9
January 2012GoodGoodGoodGood3974.0
January 2010GoodGoodGoodGood3974.0
January 2008GoodGoodGoodGood3974.0
January 2006GoodGoodGoodGood3974.0
February 2004FairGoodGoodSatisfactory3973.7
January 2002GoodGoodGoodVery Good3973.7
February 2000FairGoodSatisfactoryVery Good3973.7
February 1998FairGoodSatisfactoryVery Good3973.7
February 1997GoodGoodGoodVery Good3973.7
March 1996GoodGoodGoodVery Good3974.5
February 1995GoodGoodGoodVery Good3944.7
February 1993GoodGoodGoodVery Good3949.3
March 1991GoodGoodGoodVery Good3949.3