Facts

Source: National Bridge Inventory. Information not verified; use at your own risk.
Name:SR 64 over MAUCKS POND
Structure number:022840
Location:4.21 W SR 65
Purpose:Carries highway over waterway
Route classification:Minor Arterial (Rural) [06]
Length of largest span:198.2 ft. [60.4 m]
Total length:349.1 ft. [106.4 m]
Roadway width between curbs:22.0 ft. [6.7 m]
Deck width edge-to-edge:23.0 ft. [7.0 m]
Vertical clearance above deck:14.8 ft. [4.5 m]
Owner:State Highway Agency [01]
Year built:1931
Year reconstructed:1979
Historic significance:Bridge is possibly eligible for the National Register of Historic Places [3]
Design load:M 18 / H 20 [4]
Main span material:Steel [3]
Main span design:Truss - Thru [10]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Monolithic Concrete (concurrently placed with structural deck) [1]

Latest Available Inspection: July 2009

Good/Fair/Poor Condition:Poor
Status:Open, no restriction [A]
Average daily traffic:9,444 [as of 2004]
Truck traffic:10% of total traffic
Deck condition:Good [7 out of 9]
Superstructure condition:Poor [4 out of 9]
Substructure condition:Fair [5 out of 9]
Structural appraisal:Meets minimum tolerable limits to be left in place as is [4]
Deck geometry appraisal:Basically intolerable requiring high priority of replacement [2]
Water adequacy appraisal:Equal to present minimum criteria [6]
Roadway alignment appraisal:Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Channel protection:Bank is beginning to slump. River control devices and embankment protection have widespread minor damage. There is minor stream bed movement evident. Debris is restricting the channel slightly. [6]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Sufficiency rating:49.5
Recommended work:Replacement of bridge or other structure because of relocation of road. [32]
Estimated cost of work:$2,217,000

Previous Inspections

DateConditionDeckSuperstructureSubstructureADTSuff. Rating
July 2009PoorGoodPoorFair944449.5
June 1999FairGoodFairFair821648.3
October 1989FairSatisfactoryFairFair510060.4