Facts

Source: National Bridge Inventory. Information not verified; use at your own risk.
Name:W 157TH ST 103 over SWITZLER CREEK
Structure number:000700977604680
Location:1.7N 1.4W OF BURLINGAME
Purpose:Carries highway over waterway
Route classification:Minor Collector (Rural) [08]
Length of largest span:36.4 ft. [11.1 m]
Total length:38.4 ft. [11.7 m]
Roadway width between curbs:16.1 ft. [4.9 m]
Deck width edge-to-edge:16.1 ft. [4.9 m]
Owner:County Highway Agency [02]
Year built:1920
Historic significance:Bridge is possibly eligible for the National Register of Historic Places [3]
Main span material:Steel [3]
Main span design:Girder and floorbeam system [03]
Deck type:Corrugated Steel [6]
Wearing surface:Gravel [8]

Latest Available Inspection: August 2017

Good/Fair/Poor Condition:Poor
Status:Posted for load [P]
Average daily traffic:30 [as of 2016]
Deck condition:Poor [4 out of 9]
Superstructure condition:Poor [4 out of 9]
Substructure condition:Serious [3 out of 9]
Structural appraisal:Basically intolerable requiring high priority of corrrective action [3]
Deck geometry appraisal:Basically intolerable requiring high priority of corrrective action [3]
Water adequacy appraisal:Equal to present minimum criteria [6]
Roadway alignment appraisal:Equal to present desirable criteria [8]
Channel protection:Bank protection has failed. River control devices have been destroyed. Stream bed aggradation, degradation or lateral movement has changed the channel to now threaten the bridge and/or approach roadway. [3]
Scour condition:Bridge foundations determined to be stable for assessed or calculated scour conditions; field review indicates action is required. [4]
Sufficiency rating:26.5
Recommended work:Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Estimated cost of work:$320,000

Previous Inspections

DateConditionDeckSuperstructureSubstructureADTSuff. Rating
August 2017PoorPoorPoorSerious3026.5
August 2016PoorPoorPoorSerious3026.5
November 2015PoorPoorPoorSerious3026.5
January 2015PoorPoorPoorSerious3026.5
December 2013PoorFairFairPoor3035.6
October 2012PoorFairFairPoor3035.6
May 2011PoorFairFairPoor3035.6
May 2010PoorFairFairPoor3035.6
January 2009PoorFairFairPoor3035.6
December 2005PoorFairFairPoor3035.6
December 2003PoorFairFairPoor3035.6
February 2001PoorFairFairPoor3033.6
March 1999PoorFairFairPoor3033.8
January 1997PoorFairFairPoor3034.6
February 1995FairFairFairFair3049.6
November 1993FairFairFairFair3049.6
December 1990PoorSatisfactoryFairPoor3026.4