Share:

HINCHMAN ROAD over HICKORY DRAIN

Map

Coordinates:
+41.97111, -86.48265
41°58'16" N, 86°28'58" W

Facts

Source: National Bridge Inventory. Information not verified; use at your own risk.
Name:HINCHMAN ROAD over HICKORY DRAIN
Structure number:000000000013093
Old structure number:11200025000B020 (from 1992 edition)
Location:0.25 MI W OF LINCOLN AVE
Purpose:Carries highway over waterway
Route classification:Minor Arterial (Rural) [06]
Length of largest span:6.6 ft. [2.0 m]
Total length:22.0 ft. [6.7 m]
Owner:County Highway Agency [02]
Year built:1956
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Design load:MS 18 / HS 20 [5]
Number of main spans:2
Main spans material:Steel [3]
Main spans design:Culvert [19]
Deck type:Not applicable [N]

Latest Available Inspection: June 2018

Good/Fair/Poor Condition:Poor
Status:Open, no restriction [A]
Average daily traffic:1,521 [as of 2007]
Truck traffic:4% of total traffic
Structural appraisal:Meets minimum tolerable limits to be left in place as is [4]
Water adequacy appraisal:Meets minimum tolerable limits to be left in place as is [4]
Roadway alignment appraisal:Equal to present desirable criteria [8]
Channel protection:Bank is beginning to slump. River control devices and embankment protection have widespread minor damage. There is minor stream bed movement evident. Debris is restricting the channel slightly. [6]
Culvert condition:Large spalls, heavy scaling, wide cracks, considerable efflorescence or opened construction joint permitting loss of backfill. Considerable settlement or misalignment. Considerable scouring or erosion at curtain walls, wingwalls or pipes. Metal culverts have significant distortion and deflection throughout, extensive corrosion or deep pitting. [4]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Sufficiency rating:67.5
Recommended work:Bridge rehabilitation because of general structure deterioration or inadequate strength. [35]
Estimated cost of work:$180,000

Previous Inspections

DateConditionCulvert ConditionADTSuff. Rating
June 2018Poor4 out of 10152167.5
June 2016Poor4 out of 10152167.5
June 2014Poor4 out of 10152167.5
June 2012Poor4 out of 10152167.5
June 2010Poor4 out of 10152167.5
June 2008Fair5 out of 10152183.5
June 2006Fair5 out of 10169983.5
August 2004Fair5 out of 10169988.5
June 2002-N out of 10169696.7
January 2002Good7 out of 10169696.7