Share:

COUNTY RD 402 over NODAWAY RVR

This bridge is no longer in the current National Bridge Inventory database, and has likely been demolished or abandoned.

Map

Coordinates:
+39.93716, -94.99808
39°56'14" N, 94°59'53" W

Facts

Source: National Bridge Inventory. Information not verified; use at your own risk.
Name:COUNTY RD 402 over NODAWAY RVR
Structure number:23303
Old structure number:4020000 002 (from 1992 edition)
Location:S 13 T 59 N R 37 W
Purpose:Carries highway over waterway
Route classification:Local (Rural) [09]
Length of largest span:69.9 ft. [21.3 m]
Total length:170.0 ft. [51.8 m]
Roadway width between curbs:20.3 ft. [6.2 m]
Deck width edge-to-edge:20.7 ft. [6.3 m]
Owner:County Highway Agency [02]
Year built:1930
Historic significance:Historical significance is not determinable at this time [4]
Main span material:Steel [3]
Main span design:Truss - Thru [10]
Deck type:Wood or Timber [8]
Wearing surface:Wood or Timber [7]

Latest Available Inspection: February 2008

Good/Fair/Poor Condition:Poor
Status:Bridge closed to all traffic [K]
Average daily traffic:20 [as of 2008]
Truck traffic:10% of total traffic
Deck condition:Fair [5 out of 9]
Superstructure condition:Fair [5 out of 9]
Substructure condition:Critical [2 out of 9]
Deck geometry appraisal:Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Water adequacy appraisal:Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Roadway alignment appraisal:Equal to present minimum criteria [6]
Channel protection:Bank is beginning to slump. River control devices and embankment protection have widespread minor damage. There is minor stream bed movement evident. Debris is restricting the channel slightly. [6]
Scour condition:Bridge foundations determined to be stable for assessed or calculated scour conditions; field review indicates action is required. [4]
Sufficiency rating:38.0
Recommended work:Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Estimated cost of work:$675,000

Previous Inspections

DateConditionDeckSuperstructureSubstructureADTSuff. Rating
February 2008PoorFairFairCritical2038.0
March 1998FairSatisfactorySatisfactorySatisfactory2052.1
March 1990FairSatisfactorySatisfactoryVery Good4049.1