MO 58 E over BRIAR CR
This bridge is no longer in the current National Bridge Inventory database, and has likely been demolished or abandoned.
Map
Coordinates:
+38.71706, -93.8418238°43'01" N, 93°50'31" W
Facts
Source: National Bridge Inventory. Information not verified; use at your own risk.
Name: | MO 58 E over BRIAR CR |
Structure number: | 5796 |
Old structure number: | K 384 1 (from 1992 edition) |
Location: | S 1 T 45 N R 27 W |
Purpose: | Carries highway over waterway |
Route classification: | Minor Arterial (Rural) [06] |
Length of largest span: | 41.3 ft. [12.6 m] |
Total length: | 95.1 ft. [29.0 m] |
Roadway width between curbs: | 22.0 ft. [6.7 m] |
Deck width edge-to-edge: | 24.9 ft. [7.6 m] |
Skew angle: | 30° |
Owner: | State Highway Agency [01] |
Year built: | 1935 |
Historic significance: | Bridge is not eligible for the National Register of Historic Places [5] |
Design load: | M 13.5 / H 15 [2] |
Number of main spans: | 3 |
Main spans material: | Steel [3] |
Main spans design: | Stringer/Multi-beam or girder [02] |
Deck type: | Concrete Cast-in-Place [1] |
Wearing surface: | Bituminous [6] |
Latest Available Inspection: December 2016
Good/Fair/Poor Condition: | Poor |
Status: | Posted for load [P] |
Average daily traffic: | 2,093 [as of 2015] |
Truck traffic: | 10% of total traffic |
Deck condition: | Serious [3 out of 9] |
Superstructure condition: | Fair [5 out of 9] |
Substructure condition: | Fair [5 out of 9] |
Structural appraisal: | Meets minimum tolerable limits to be left in place as is [4] |
Deck geometry appraisal: | Basically intolerable requiring high priority of replacement [2] |
Water adequacy appraisal: | Equal to present minimum criteria [6] |
Roadway alignment appraisal: | Equal to present desirable criteria [8] |
Channel protection: | Bank is beginning to slump. River control devices and embankment protection have widespread minor damage. There is minor stream bed movement evident. Debris is restricting the channel slightly. [6] |
Scour condition: | Bridge foundations determined to be stable for the assessed or calculated scour condition. [8] |
Sufficiency rating: | 20.3 |
Recommended work: | Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31] |
Estimated cost of work: | $719,000 |
Previous Inspections
Date | Condition | Deck | Superstructure | Substructure | ADT | Suff. Rating |
---|
December 2016 | Poor | Serious | Fair | Fair | 2093 | 20.3 |
December 2015 | Poor | Serious | Fair | Fair | 2023 | 20.3 |
December 2014 | Poor | Serious | Fair | Fair | 2023 | 20.3 |
December 2013 | Poor | Serious | Fair | Fair | 2276 | 20.3 |
December 2012 | Poor | Serious | Fair | Fair | 2276 | 20.3 |
November 2011 | Poor | Serious | Fair | Fair | 2299 | 20.3 |
January 2011 | Fair | Fair | Fair | Satisfactory | 2157 | 26.6 |
October 2009 | Fair | Fair | Fair | Satisfactory | 2249 | 26.0 |
October 2008 | Fair | Fair | Fair | Satisfactory | 2249 | 26.0 |
September 2006 | Fair | Fair | Fair | Satisfactory | 2543 | 25.2 |
January 2006 | Fair | Fair | Satisfactory | Satisfactory | 2553 | 38.6 |
October 2004 | Fair | Fair | Satisfactory | Satisfactory | 2498 | 38.9 |
January 2004 | Fair | Fair | Satisfactory | Satisfactory | 2528 | 38.8 |
February 2003 | Fair | Fair | Satisfactory | Satisfactory | 2506 | 38.9 |
February 2002 | Fair | Fair | Satisfactory | Satisfactory | 2438 | 39.2 |
December 1999 | Fair | Fair | Satisfactory | Satisfactory | 2257 | 38.9 |
December 1998 | Fair | Fair | Satisfactory | Satisfactory | 2257 | 38.9 |
January 1998 | Fair | Fair | Satisfactory | Satisfactory | 2257 | 38.9 |
February 1996 | Poor | Fair | Poor | Satisfactory | 2025 | 9.3 |
February 1995 | Poor | Fair | Serious | Satisfactory | 1947 | 6.0 |
January 1994 | Fair | Fair | Fair | Satisfactory | 1883 | 27.0 |
October 1992 | Fair | Fair | Fair | Satisfactory | 1883 | 27.0 |
November 1991 | Fair | Fair | Fair | Satisfactory | 1795 | 27.6 |