Facts

Source: National Bridge Inventory. Information not verified; use at your own risk.
Name:PR 102 over UNNAMED CREEK
Structure number:002031
Location:8.7 KM NORTH OF CABO ROJO
Purpose:Carries highway over waterway
Route classification:Minor Arterial (Rural) [06]
Length of largest span:23.0 ft. [7.0 m]
Total length:23.0 ft. [7.0 m]
Roadway width between curbs:19.7 ft. [6.0 m]
Deck width edge-to-edge:23.3 ft. [7.1 m]
Owner:State Highway Agency [01]
Year built:1940
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Main span material:Concrete [1]
Main span design:Slab [01]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Bituminous [6]

Latest Available Inspection: May 2018

Good/Fair/Poor Condition:Poor
Status:Posted for load [P]
Average daily traffic:6,500 [as of 2000]
Truck traffic:5% of total traffic
Deck condition:Poor [4 out of 9]
Superstructure condition:Poor [4 out of 9]
Substructure condition:Fair [5 out of 9]
Structural appraisal:Meets minimum tolerable limits to be left in place as is [4]
Deck geometry appraisal:Basically intolerable requiring high priority of replacement [2]
Water adequacy appraisal:Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Roadway alignment appraisal:Equal to present desirable criteria [8]
Channel protection:Bank protection is being eroded. River control devices and/or embankment have major damage. Trees and rush restrict the channel. [5]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Sufficiency rating:15.1
Recommended work:Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Estimated cost of work:$180,000

Previous Inspections

DateConditionDeckSuperstructureSubstructureADTSuff. Rating
May 2018PoorPoorPoorFair650015.1
May 2016PoorPoorPoorFair650012.1
April 2015PoorPoorPoorFair650012.3
March 2014PoorPoorPoorFair650012.1
March 2012PoorPoorPoorFair700033.0
April 2010PoorPoorPoorFair700033.0
January 2008PoorFairPoorFair840035.0
May 2006PoorFairPoorFair840011.8
September 2004PoorFairPoorFair840011.8
September 2001PoorGoodPoorFair710012.8
August 1999PoorGoodPoorFair710012.8
September 1997PoorPoorPoorFair870010.8
April 1996PoorPoorPoorSatisfactory670013.8
June 1994PoorPoorPoorSatisfactory640013.8
July 1992PoorPoorPoorSatisfactory620013.8
February 1991PoorPoorPoorSatisfactory616014.8

Element Data

Source: National Bridge Elements dataset, 2019 edition. This feature is experimental.
ElementUnitsQuantity1-Good2-Fair3-Poor4-Serious
Substructure
Reinforced Concrete Abutmentlinear ft.89622070
Bridge Rail
Reinforced Concrete Bridge Raillinear ft.8978200
Deck
Reinforced Concrete Slabsq. ft.45233397220
Wearing Surfacessq. ft.4523985400