Share:

PR 2 over MAGINA CREEK

Map

Coordinates:
+18.03000, -66.94000
18°01'48" N, 66°56'24" W

Facts

Source: National Bridge Inventory. Information not verified; use at your own risk.
Name:PR 2 over MAGINA CREEK
Structure number:016631
Location:6.5 KM N W OF GUANICA
Purpose:Carries highway over waterway
Route classification:Principal Arterial - Interstate (Rural) [01]
Length of largest span:12.5 ft. [3.8 m]
Total length:24.9 ft. [7.6 m]
Owner:State Highway Agency [01]
Year built:1979
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Design load:MS 18 / HS 20 [5]
Number of main spans:2
Main spans material:Concrete [1]
Main spans design:Culvert [19]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Monolithic Concrete (concurrently placed with structural deck) [1]

Latest Available Inspection: May 2018

Good/Fair/Poor Condition:Fair
Status:Open, no restriction [A]
Average daily traffic:25,926 [as of 2003]
Truck traffic:5% of total traffic
Structural appraisal:Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Water adequacy appraisal:Superior to present desirable criteria [9]
Roadway alignment appraisal:Equal to present desirable criteria [8]
Channel protection:Bank is beginning to slump. River control devices and embankment protection have widespread minor damage. There is minor stream bed movement evident. Debris is restricting the channel slightly. [6]
Pier/abutment protection:Navigation protection not required [1]
Culvert condition:Moderate to major deterioration or disintegration, extensive cracking and leaching or spalls on concrete or masonry walls and slabs. Minor settlement or misalignment. Noticeable scouring or erosion at curtain walls, wingwalls or pipes. Metal culverts have significant distortion and deflection in one section, significant corrosion or deep pitting. [5]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Sufficiency rating:59.0
Recommended work:Bridge rehabilitation because of general structure deterioration or inadequate strength. [35]
Estimated cost of work:$846,000

Previous Inspections

DateConditionCulvert ConditionADTSuff. Rating
May 2018Fair5 out of 102592659.0
April 2016Fair5 out of 102592659.0
April 2014Fair5 out of 102640059.0
May 2012Fair5 out of 102640059.0

Element Data

Source: National Bridge Elements dataset, 2019 edition. This feature is experimental.
ElementUnitsQuantity1-Good2-Fair3-Poor4-Serious
Culvert
Reinforced Concrete Culvertlinear ft.33892184620
Bridge Rail
Steel or Aluminum Bridge Raillinear ft.5252000